-----Original Message-----
Subject: Project Objects
Hi
We have found that there are more than one WBS for an object. This is
supposed to be a unique relationship i.e. one to one.
On doing an object find for a Project Characteristic you obtain the
object numbers (that is WBS elements internal numbers) of the objects
that contain the characteristics. Using T.code SE16 you can find the WBS
element number of the object. On doing this search we have found
multiple WBS elements for the same object number. On investigating the
situation, we found that in most instances the "other" object another
WBS element in the same structure or one created shortly after the
correct WBS element.
We have not yet found out why this happens, what the solution is or if
we have found all occurrences.
Has anybody encountered something similar?
Thanks
-----Reply Message-----
Subject: RE: Project Objects
In PRPS, there is 4 fields that refer to an SAP object:
POSID is the WBS element identifyer the user see on the screen
PSPNR is the internal SAP project item number (which IS unique)
OBJNR is the SAP object number (made out prefix 'PR' and the internal
project item number. It is also the number that is stored in the Costs tables.
PSPHI is the internal current number of the project the WBS element belongs
to.
All these numbers are absolutely unique. But all WBS elements in the same
project will share the same PSPHI, which indicates the project (from the
PROJ database).
The reason why you have an internal SAP number (PSPNR) and an external
number (POSID) is to allow the user to change the WBS element identifyer
without losing all the history.
Check to make sure you were looking at the right object number.
Hope that helps,
-----End of Message-----
SD ABAP Reports, Account Payable, Availability Check, Billing, CIN,QM in Logistics, Production ,Inventory Posting, Source Inspection, MM Archiving, Certification Exam, Inventory Management, Material Master
Tuesday, June 10, 2008
Subscribe to:
Post Comments (Atom)
Archive
-
▼
2008
(198)
-
▼
June
(51)
- Step-by-Step Procedure for Customizing an Electron...
- Document flow confusion in SAP FI General Ledger
- What is "Real Time" Integration? FICO General Ledger
- Configuration for Special Purpose FICO General Ledger
- Using the Lock Box Files in SAP FICO General Ledger
- What is Hold and Parking of Document? FICO General...
- Difference between Posting Key and Field Status Va...
- Various Postings To The FICO GL Account Postings
- What is Debit note and Credit note? FICO General L...
- Sample Account Assignment in G/L Account FICO Gene...
- Some Important Tcodes for FI GL AR AP Asset
- SAP FI Transaction Code List 1
- SAP FI Transaction Code List 2
- Useful Reports Tcode in SAP Financial Accounting
- The Financial Statement Closing Tcodes
- Profit and Loss Closing FICO Tcodes
- Assets and Liabilities Closing Tcodes
- Inventory Accounting Entries FICO Account Posting
- Sales and Distribution Accounting Entries FICO Acc...
- Vendor Invoice Verification Accounting Entries FIC...
- Reversal Entry In Accounting FICO Account Posting
- Banking Transaction Financial Accounting Entries
- Important Tables in SAP FI
- Important Tables in SAP CO
- Important Tables in SAP FICO AA
- Displaying Commodity Codes and Import Code in SAP MM
- Comparison of Commodity Code Numbers in SAP MM
- Loading Commodity Codes and Import Code Numbers in...
- Loading of Commodity Codes and Import Code in SAP MM
- My SAP PM Certification Experience
- SAP PM Certification - Plant Maintenance Certifica...
- My SAP SD Certification Experience
- SAP SD Sample Certification Questions in Sales Ord...
- Basic Concept of Global ASAP
- ASAP Global Roadmap
- ASAP Phase 5: Go Live and Support
- ASAP Phase 4: Final Preparation
- ASAP Phase 3: Realization
- ASAP Phase 2: Business Blueprint
- ASAP Phase 1: Project Preparation
- Accelerated SAP ii
- Accelerated SAP Introduction
- Phases of a SAP Project (ASAP)
- Budget Exceeded Even When There is Amount Available
- CLOSING A PROJECT
- Investment Management
- Settlement From WBS to AUC that was created from o...
- Project Objects
- Various Cost Planning Methods in PS
- Asset Value Date in Settlement
- List Of User Exit Related to VL01N
-
▼
June
(51)
No comments:
Post a Comment