Thursday, October 9, 2008

SAP Milestones

----Original Message-----
Subject: Milestones

We don't use networks and activities.

The same time we want to use milestones only with WBS-elements for basic POC evaluation.

For instance for WBS we can attach several milestones with different POC, like 10%, 50%, 80%.

What is the tool in the system to confirm that particular milestone is reached? How can I change milestone status?

-----Reply Message-----
Subject: RE: Milestones

each milestone attached to a WBS element will have an actual date field open for entery when u release the WBS element. this will determine if the milestone has been achieved or not.

the %age entered in the milestone for POC will be considered in the progress analysis.

-----End of Message-----

No comments:

Archive